Hello all,
Our host has just contacted us about the final phase maintenance that is taking place tomorrow so I would just like to let you know that we may get a 20-30 minutes downtime for this reason. If you do experience a downtime tomorrow, just try again in 30 minutes and everything should be back to normal.
Thanks.
MasterA
Our host has just contacted us about the final phase maintenance that is taking place tomorrow so I would just like to let you know that we may get a 20-30 minutes downtime for this reason. If you do experience a downtime tomorrow, just try again in 30 minutes and everything should be back to normal.
Thanks.
MasterA
We are sending this advisory to inform you of an upcoming Final Phase Power maintenance to be performed in our datacenter which your server may be affected by.
Event Date(s): Friday, February 13th, 2015 from 8.00pm until 10.00pm CDT (GMT-5)
Event Location: OK-R1-R8
Impact: Up to 20-30 Mins Downtime
Event:
We are excited to announce that we are in the process of doing a major power upgrade to accommodate our growth. With this power upgrade, we decided to buy some of the latest and greatest Equipment, you can look forward to a brand new GE Spectra Bolt-On AV5 switchgear equipped with an EPM 2200 Power Meter and a designated Power Break II. Along with, a brand new EatonPower Xpert 9395 UPS that has LCD inputs and outputs. (http://bit.ly/16aHuMU).
Additionally, a third generator will be installed to increase the total non-utility power capacity. We are also upgrading the power cabling under the raised floor using red and blue PDU cables (http://bit.ly/1yDWPft).
GE Spectra Bolt-On AV5 and Eaton
Power Xpert 9395
This power upgrade is going to make our Expansion capabilities almost endless, and this gives us the opportunity to continue to grow and provide much better redundancy
As you might expect, we will eventually have to move your equipment over to the “new power.” When we do this, you could experience a small power outage. We will do our very best to make this as painless as possible.
1st Maintenance Window – January 16, 2015 to January 17, 2015 (15 to 20 Mins Downtime)
2nd Maintenance Window – January 30, 2015 to January 31, 2015 (No Downtime)
3rd Final Maintenance - February 13, 2015 (20 - 30 Mins Downtime)